Today we noticed an exciting development! Inax staff came in to install the Bath Unit yesterday. Part of the ceiling has not been finished so we expect they will be back at a later date. It's really too bad that Inax units don't accommodate inclined ceilings because that would have been really nice.
When we selected our bath unit, we may have not paid much attention to the door. It seemed a little flimsy to me when I saw it today, so I hope it'll stand the test of time in our home... Other than that, we love it, especially the large window!
On the first floor, Fukuzumi-san was nearly done covering the walls with plaster board. He finished the recessed ceiling in the Living Room. We decided we would paint the ceiling and the beams white.
The unit comes as a type of rectangular box, with a flat ceiling, and all of the equipment we previously selected. We noticed they installed three shelves for shampoos and soaps, even though we specifically requested only two. But this is definitely not such a big deal; we can live with it, especially since the shelves come off easily for cleaning.
We did get the shower bar from a different series that we had asked for. Inax was unable to accommodate that request directly, but our contractor got us our wish.
On the first floor, Fukuzumi-san was nearly done covering the walls with plaster board. He finished the recessed ceiling in the Living Room. We decided we would paint the ceiling and the beams white.
We also noticed that he had installed the frame for the Living Room sliding doors.
Meanwhile on the second floor, Fukuzumi-san Junior was working on our Master Bedroom closets frames.
After 3 days straight of rain, the subcontractors in charge of installing the lath on the exterior walls were back today, finishing things up. The mortar should be applied next. We'll go back some time later this week to check on the progress.